Q-2, r. 17.1 - Regulation respecting the regulatory scheme applying to activities on the basis of their environmental impact

Full text
199. The addition and replacement of a mains and any other equipment serving a single building to the system are exempted from authorization pursuant to this Subdivision when the specifications for the work are prepared in accordance with the standard specification BNQ 1809-300 or at least meet the requirements of that specification for the work concerned.
O.C. 871-2020, s. 199.
In force: 2020-12-31
199. The addition and replacement of a mains and any other equipment serving a single building to the system are exempted from authorization pursuant to this Subdivision when the specifications for the work are prepared in accordance with the standard specification BNQ 1809-300 or at least meet the requirements of that specification for the work concerned.
O.C. 871-2020, s. 199.